To strengthen and expand our business operations in Myanmar, after careful consideration, it has been decided to send Shang Hongyi from Tianjin Machinery Import & Export Co., Ltd.—a subsidiary of our group—to Myanmar on July 20, 2023, to discuss business opportunities. He is expected to stay abroad for approximately 50 days.
The Myanmar Dabang 60-ton-per-day newsprint mill project completed equipment trial runs in 2017 and received the final acceptance report. However, full payment for all equipment purchases wasn’t settled until 2019. Since then, the paper mill has remained non-operational due to several factors, including a severe shortage of natural gas—a critical energy source—and personnel changes within relevant government departments.
Recently, the Myanmar paper mill unexpectedly reached out to our company, informing us that they are now ready to begin trial runs of the equipment under no-load conditions, followed by load testing and eventual production operations. They’ve expressed their desire for our engineering team to promptly dispatch technical experts to the site to provide on-site guidance and ensure smooth equipment startup and operation.
We held urgent discussions with Myanmar’s paper mills, relevant departments, and other stakeholders regarding the project budget, the size of the project team, and the project timeline. After finalizing all key details, we decided to send a representative to assist the Myanmar side in completing the commissioning tasks. Given that this production line involves a significant number of equipment pieces, there’s potential for the project to progress more slowly. Therefore, we’ve requested a total of 50 days for the entire commissioning process.
The expenses related to the delegation will be borne by Tianjin Machinery Import & Export Co., Ltd. and have already been included in the company's current-year budget for temporary official overseas (or border-crossing) travel expenses, totaling approximately 70,552 yuan.
Details of the visiting delegation:
Shang Hongyi, Male, 1975/01/08
Tianjin Machinery Import & Export Co., Ltd. – Sales Representative (Team Leader)
June 12, 2023
Tianjin Machinery Import & Export Co., Ltd.
Comrade Shang Hongyi's Travel Schedule to Myanmar
| Date |
Plan |
| 7-20 |
Morning: Arrive in Yangon Afternoon: Arrive in Dabang |
| 7 Month 21 Day -7 Month 23 Day |
Morning: Gaining insight into the on-site production line situation Afternoon: Assessing the Skill Levels of Local Technical Workers |
| 7 Month 24 Day -7 Month 30 Day |
Morning: Supervising and guiding in the pulp workshop Afternoon: Supervising and guiding in the pulp workshop |
| 7 Month 31 Day -8 Month 6 Day |
Morning: Supervising and guiding operations in the papermaking workshop Afternoon: Supervising and guiding in the papermaking workshop |
| 8 Month 7 Day -8 Month 13 Day |
Morning: Supervising and guiding operations in the papermaking workshop Afternoon: Supervising and guiding in the papermaking workshop |
| 8 Month 14 Day -8 Month 20 Day |
Morning: Supervising and guiding in the material preparation workshop Afternoon: Supervising and guiding in the material preparation workshop |
| 8 Month 21 Day -8 Month 27 Day |
Morning: Supervising and guiding at the wastewater workshop Afternoon: Supervising and guiding at the power station |
| 8 Month 28 Day -9 Month 3 Day |
Morning: Acceptance Testing Afternoon: Acceptance Testing |
| 9 Month 4 Day -9 Month 5 Day |
Morning: Acceptance Testing Afternoon: Acceptance Testing |
| 9 Month 6 Day |
Morning: Acceptance testing completed Afternoon: Acceptance testing completed |
| 9 Month 7 Day |
Arriving in China |